SpecPlate NOX

SpecPlate NOX is a well graded blend of nonoxidizing metallic aggregates, plasticizer and cement
binder. It provides maximum abrasion-resistance to interior concrete floors. When incorporated into fresh concrete slabs, SpecPlate NOX will provide a surface which is highly resistant to abrasion, impact and point loading even in areas subject to frequent moisture and water exposure.

  • Provides a non-rusting, high strength wearing surface in areas subjected to frequent moisture and water.
  • Increases impact and abrasion resistance up to eight times that of plain concrete
  • Provides a high density surface that resists liquid penetration and is easy to clean and maintain
  • Resistant to surface dusting, spalling, and deterioration due to abrasion.
  •  Light Reflective formula offers improved lighting and reduced energy cost.

Coverage

  • 1.5 to 2.5 lbs per sq. ft.

Packaging

  • 50lb triple lined bag (22.7 kg)

Shelf Life

Shelf life of unopened bags stored in a dry facility is 12 months. Excessive temperature differential and/or high humidity can shorten the shelf life expectancy. Store in a cool, dry area away from direct sunlight.

Standards

  • U.S.D.A. accepted for use in facilities where incidental contact with food product is possible.
  • Compliant with American Concrete Institute Standards: ACI 302, ACI 305, ACI 306

Application Guidelines:

  • Follow the American Concrete Institute Standard 302 for general floor and slab construction guidelines.
  • Aim to perform all work under a roof whenever possible. Environmental conditions that affect drying and setting times will also impact the timing of hardener application.
  • Proper concrete mix design must be reviewed and approved by SpecChem before placement.
  • Prepare the area by calculating the required number of bags based on the coverage rate, and ensure the concrete is placed to the finish grade level and compacted with a wooden bull float.

Special Conditions:

  • Apply SpecFilm to the surface immediately after bull floating in conditions that promote rapid surface drying, such as low humidity, wind, or sunlight.

Placing the Hardener:

  • The application should consider the concrete slump, job site conditions affecting drying, and the necessary coverage. Begin application at the perimeter as it sets quicker than the interior.
  • Use a dry-shake method after concrete bleeding. Apply two-thirds of the hardener initially, allow it to absorb moisture, then float. Follow immediately with the remaining one-third and complete the machine float after the slab stiffens.

Curing:

  • Apply an approved SpecChem ASTM C-309 compliant curing compound post-final troweling to ensure optimal curing.
Compressive Strength
ASTM C109
SpecPlate NOX
Mixed at 9.5% water
7 Days 9,750 psi
28 Days 12,500 psi

Coverage

  • 1.5 to 2.5 lbs per sq. ft.

Packaging

  • 50lb triple lined bag (22.7 kg)

Shelf Life

Shelf life of unopened bags stored in a dry facility is 12 months. Excessive temperature differential and/or high humidity can shorten the shelf life expectancy. Store in a cool, dry area away from direct sunlight.

Standards

  • U.S.D.A. accepted for use in facilities where incidental contact with food product is possible.
  • Compliant with American Concrete Institute Standards: ACI 302, ACI 305, ACI 306

Application Guidelines:

  • Follow the American Concrete Institute Standard 302 for general floor and slab construction guidelines.
  • Aim to perform all work under a roof whenever possible. Environmental conditions that affect drying and setting times will also impact the timing of hardener application.
  • Proper concrete mix design must be reviewed and approved by SpecChem before placement.
  • Prepare the area by calculating the required number of bags based on the coverage rate, and ensure the concrete is placed to the finish grade level and compacted with a wooden bull float.

Special Conditions:

  • Apply SpecFilm to the surface immediately after bull floating in conditions that promote rapid surface drying, such as low humidity, wind, or sunlight.

Placing the Hardener:

  • The application should consider the concrete slump, job site conditions affecting drying, and the necessary coverage. Begin application at the perimeter as it sets quicker than the interior.
  • Use a dry-shake method after concrete bleeding. Apply two-thirds of the hardener initially, allow it to absorb moisture, then float. Follow immediately with the remaining one-third and complete the machine float after the slab stiffens.

Curing:

  • Apply an approved SpecChem ASTM C-309 compliant curing compound post-final troweling to ensure optimal curing.
Compressive Strength
ASTM C109
SpecPlate NOX
Mixed at 9.5% water
7 Days 9,750 psi
28 Days 12,500 psi